falconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond reputefalconfixer has a reputation beyond repute
Default Z1 Motorsports 25 row oil cooler install

I installed the Z1 Motorsports 25 row oil cooler this weekend in a matter of about 5 hours. The kit itself is great and thanks to John@Z1 for the deal. I also have to point out these guys hook it up as I ordered it and it was at my house two days later. The kit was packaged very well and everything was supplied. Even got some stickers for an added 25hp boost. The supplied instructions are some of the best I’ve seen for aftermarket installs but I wanted to add some ideas here that might make it a little bit easier for the next guy. The main thing is the instructions state to take the passenger front wheel off and I can tell you this is not needed. Also, I felt there were different ways to go about the steps and still end up with the same result.

This was installed on a 2011 Touring so you NISMO guys have some other steps you'll have to take.


Tools needed:
Jack and jack stands or ramps
4mm Allen key
10mm socket
12mm socket
Ratchet
Couple of extensions
10mm combo wrench
25mm combo wrench OR a big crescent wrench
25mm or 1” socket
Torque wrench
Flat head screwdriver
Drill and drill bits ranging in size up to ¼ inch
Piece of scrap wood

Consumables:
Safety wire or equivalent
Lock-tite
Zip-ties (if not provided)
Engine oil
Oil filer

1.In the cozy confines of your work shop/garage/living room become familiar with the supplied instructions from Z1 Motorsports. This is a good time to install the brackets to the oil cooler itself and insure you have all the needed hardware before tearing the car down. You will need a 4mm allen key and 10mm wrench/socket.
2.Get the front end off the ground.
3.Remove bumper. Thanks to DIGItonium’s write up that can be found here DIY: Front Bumper Removal



4.If you are planning on changing the oil in conjunction with this install (I did) remove the plastic shroud underneath the car. Refer to AK370’s write-up here DIY: Nissan 370Z Oil change (AK370Z way) Pictures inside
5.Remove crash bar using 12mm socket. There are 4 nuts and 4 bolts holding it on.



6.Remove 3 ea. 10mm bolts holding the windshield washer reservoir in place. This is tricky to balance so a friend may come in handy here. I didn’t feel like disconnecting the supply line and have fluid everywhere so I used some safety wire and hung it off to the side. It gave me some needed room for later steps.
7.Remove 4 ea. 10mm bolts securing the power steering cooler. Three of them will be right in front of you and one will be tucked up in there. This will be the one you also add the spacer to when routing your oil cooler lines.




8.Install the supplied 2 ea. nutplates on the core support and have the upper bracket sitting on the forward side on center brace. This gives you a template of where to drill to secure the upper mount fastener. I used the smallest drill bit I had to score the metal. Do NOT drill trough at this time.



9.Remove the cooler and set aside.
10.Place your piece of scrap wood behind where you are going to drill. Please do not forget this as there is a good chance the drill will punch right through the metal and into your radiator. Drill the hole up to at least ¼ inch in diameter. This is all I needed to fit the upper mount bolt through.
11. Install the oil cooler.
12.This is where I deviated from the instructions supplied from Z1. It says to fill the cooler up and install the lines. I choose to hold off and install the lines to the thermostatic plate first and wait on the oil cooler side.
13.Follow the instructions from Z1 and route the two oil cooler lines along the right side between the power steering bracket and body, through the frame (yes, I know we are unibody but you get the point) and get you some slack near the oil filter.
14.How you go about the next few steps is up to you but here is what I did. I drained the oil and removed the oil filter at this point.
15.Get your thermostatic plate in hand and lube the O-rings on the fittings. Tighten those down. The biggest wrench I have is 24mm and it looked like a 25mm would work but I used a crescent wrench.
16.Once everything was drained I fought with and finally got the oil cooler lines installed on the plate. Refer to Z1’s instructions. They recommend fitting the lines to the plate, tighten till snug, remove the plate, torque lines down, and install the plate at 10 o’clock position for 09-11 and 7 o’clock position for 2012’s. I got everything finally tightened down and you will too with some creativity and cuss words. Don’t forget to use some fresh engine oil to lube up the O-ring on the plate before torquing it down to the block-I had a 1” socket the fit perfectly and torqued to 25 ft/lbs. This is also where it was very handy to have the other end of the lines not connected to the cooler as I could manipulate them around.
17.Whew, that was the hard part!! At this point I re-installed the power steering bracket with the supplied spacer and started routing my lines back to the oil cooler.



18.Following the supplied instructions I took the caps off the oil cooler and started pouring fresh oil in it. Take this step slow. I went a little too fast and ended up with oil burping out and making a mess. Lube up the O-rings on the fittings with fresh oil and tighten them down.
19.Install the lines and make sure there are no kinks and everything looks good.
20.Install the windshield washer reservoir.
21.If you drained the oil during this task make sure your plug is in and a new filter is installed. Fill the block up with fresh oil. I started with 5 1/8 quarts.
22.Clean everything off around the fitting and start the car. Check for any leaks and fix as required.
23.Zip tie the lines neatly and out of the way.
24.Install the crash bar. I used the Lock-tite here.



25.Install the bottom shroud.
26.Install the bumper.
27.Put the car on the ground and double and triple check oil level. I ended pouring approx 6 ¾ quarts of oil in to hit the H mark on the dipstick but like I said, I spilled some while filling the cooler itself.

I was hitting 250-260 on spirited runs in the high 90s but the weather has cooled down a little. Took the car out Sunday and the temp outside was high 80s but never got above 190 oil temp per the guage. Sure, it takes a little longer to come up to temp but I went into this knowing that. For the winter months I'll just install a shroud over the cooler.